The Tagged Story Burndown Chart displays work remaining to deliver a story or a feature (epic story) supported by a group of stories identified by a common tag. Each day, the estimated work remaining to deliver a story is calculated and graphed, resulting in a Burndown chart.  Stories are frequently scheduled by many teams across many iterations and releases. As a result, the Tagged Story Burndown Chart is an effective way to report on features and/or products worked on by multiple teams by leveraging a common tag identifying the various parts of that feature/product.

Story Metrics are displayed above the Tagged Story Burndown Chart. Metrics include the following information:

  • Estimated - Plan Estimate
  • Tasked - How many Stories have at least one task
  • Scheduled in a Release - How many Stories are scheduled in a release
  • # of Points vs. # of Accepted - Points of estimated child stories

The green bars indicate accepted work and the blue bar indicates remaining task hours. The amount of work remaining (Task To Do and Accepted) becomes smaller and smaller as development progresses until it reaches point 0. Red dotted lines indicate Release Dates.

To display a Tagged Story Burndown Chart, enter a tag (the tag must include at least 1 character) in the Tag text box.

Tagged Story Burndown

To access the Tagged Story Burndown chart:, select the main Reports tab. This tab shows all available reports/charts in a consolidated view with additional functionality such as email, print with annotation, and save as .jpg or .pdf formats.